Yes, the Play Park was officially opened on Friday 08 November 2019 by the Head Girl, Jessica Anthony and Head Boy, Euan Whiddett from North Queensferry Primary School.

Also, the ship was launched and named by Sofia and Charlotte Haigh, who won the "Name the Ship" competition at the Village Show in 2018. The name being, "The Ferry Belle."

Special guests were Joshua Haynes (Mack) and James McKenzie (James) from the BBC Series of "Molly and Mack."

A fantastic day out and even the weather was perfect.

 

 

Official Opening of the Play Park

The Pierhead Play Park will be officially opened on Friday 08 November 2019 at 1.30pm. The Head Boy and Head Girl from North Queensferry Primary School will do the honours.

Also, there will be the launching and naming of the ship.

Everybody is welcome to come along and support this milestone.  

 

Nearing Completion (October 2019)

The refurbishment of the Play Park is moving on at a good pace now, with turf laying and landscaping in progress. The Play Park sign has been delivered and will be located within the park perimeter.

By the end of October 2019 the park may look complete, but the turf requires a few weeks to bed-in. Also, an independent inspection is required by the Royal Society for the Prevention of Accidents (RoSPA) and a Safety Certificate issued prior to opening the park to the public. So the official opening will be in November 2019. The date has yet to be confirmed.    

 

Edit this text

Suspension of Construction Work

Work on site was suspended on Thursday 29 August 2019 for 3 days following an objection. Further to a formal meeting held on Tuesday 03 September 2019, work re-commenced on site.

The Project Group and representation from Fife Council have agreed to give a report to the North Queensferry Community Council on Thursday 12 September 2019.

 

Test Bores on Wednesday 14 August 2019

The Contractor will be on Site on Wednesday 14 August 2019 to carry out test bores and determine the ground conditions.

This operation should only last for one day and take place during normal working hours. Residents local to the Play Park have been informed through the issue of "Flyers" to each household.  

Award of Contract

We are pleased to announce that Hawthorn Heights have been awarded the contract to refurbish the play park.

The procurement of the equipment is currently on-going and the latest date received for work commencing on site is Monday 26 August 2019.

Will keep you posted!!